KLE LNG Train 1 – Fractionation Upgrade

Project Overview:

The KLE LNG Train 1 Fractionation Unit Upgrade was a key component of the Karratha Life Extension (KLE) program. This project aimed to enhance the operational reliability and safety of the LNG Train 1 Fractionation Unit through comprehensive upgrade works. Altrad (formerly AGC) was contracted to deliver a range of specialised services, leveraging a multi-disciplined workforce to complete the works within a six-week outage period.

Scope:

  • Installation of scaffolding to access over 2 km of piping and 14 vessels.
  • Removal of insulation and subsequent blast and paint works.
  • Reinstatement of insulation and cladding.
  • Passive fire protection applications.
  • Workpack preparation and delivery of specialised mechanical services.

Manning:

  • Peak manning:379 personnel.
  • Total man-hours: 356,795.

Outcomes:

  • Successfully resourced over 250 personnel across day and night shifts to meet the stringent six-week outage requirement.
  • Delivered all works safely within the outage timeframe, supporting uninterrupted production upon completion.
  • Reinforced Altrad’s reputation for delivering large-scale, high-complexity projects under tight schedules with exceptional safety and quality standards.
Client

Woodside Energy Pty Ltd

Location

Karratha, Western Australia

Duration

November 2014 – January 2016

Industry
Energy